PROJECT CLIENT % COMPLETION JUNE 23
Development of West Qurna-2 oilfield 77 INSAAT & SICIM 100 %
Construction of South Samarra 132 KV GIS Substation GE & MoE 100 %
Construction of West Ramadi 132 KV GIS Substation GE & MoE 95%
Construction of AL-Muthanna 400 KV GIS Substation/ Samawa Elsewedy PSP/MoE 100%
Maintenance services of the Kurdistan Pipeline stations KPC 100%
Commissioning services at Karbala Refinery Hyundai & SK 100%
Inspection and Diagnostics of Cathodic protection system at west Qurna Oil Field SICIM (Italy) 100%
Supply of Chemicals for Power Plants, Baghdad. MoE 100%
Construction of Al-Shatra 400 KV GIS Substation/Nasiriya Elsewedy PSP/MoE 100%
Construction of New Babil 400 KV GIS Substation/ Babil Elsewedy PSP/MoE 100%
Khor Mor Gas Field Development/ East Kirkuk. Dana Gas / Crescent Petroleum 90%